First Well for Chipokolo

The preparation and drilling were a major event. Not only because they marked the actual start of the project, but also because of the question of whether we would find enough water to supply the property and its buildings. And finally, there was the question of where we would find the most water, because that is where the supply building from which the distribution would originate was to be located.
Two teams of hydrologists surveyed the site, and both came to the same conclusion: the most promising drilling site was exactly where we had intuitively hoped it would be. One team leader was skeptical about the expected amount of water, while the other advised us to go ahead. We took the plunge and hired the team from the Ministry of Agriculture, Irrigation, and Water Development in Lilongwe.
They drilled 43 meters deep, partly through hard rock, to the point where it was hard to imagine going any further. A soil sample was collected from each drill rod length and evaluated by Brian, the team leader. Then came the suggestion not to drill any deeper, and for us the big question: will we get enough water?
A week later, another team arrives to test the pump. They set the pump to 37 meters, as recommended by the hydrological report. A 12-hour test is then carried out, and a few days later we receive the detailed test report: The spring delivers 0.3 liters per second, which is around 1,000 liters per hour—enough for our needs. We are all relieved, as the drilling was quite expensive. We would like to thank the German Embassy in Lilongwe for supporting the first step of the project!

Translated with DeepL.com (free version)

Similar Posts

  • Project-Presentation in Malawi

    Annie Salama, DPD Director of Planning and Development, invited us to attend the District Council meeting. Forty-three district councilors were present and asked us questions. Our planning and hygiene concept received high praise.Matias Kamanga, the CBO chair, Hilda Chonobvu, the secretary/recording secretary, Adams Milanzi, and our YOOW manager made a good impression and sparked great…

  • |

    Apprenticeship and Workshops

    It will start on May 1, 2026: we are building the vocational training workshops. Following a tender process, we have commissioned Emmanuel General Construction from Kasungu as the contractor, together with the Chiuno NGO. Five workshops, including outdoor areas, will form a small center for manual work and collaboration. A tree stands in the center and grows…

  • Malawi and Covid

    For a long time, Africa was spared from the pandemic. Now it seems to have arrived in Malawi too (Der Tagesspiegel on 23 April 2020). The entry ban has been in place for some time, so our plans were also rendered obsolete. The planned lockdown is now pending in court because the population has put…

  • CBO Training

    In Chiuno Village, where there is no running water or electricity, dealing with legal forms is also a new challenge. The community-based organization corresponds to a non-profit association in Germany at the municipal level. Here, as there, the members and their boards are subject to a set of rules based on legal requirements. The social…